A new manufacturing line project is planned to be delivered in iterations for the equipment installation phase. During one of the iterations, the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.

What should the project manager do next?

A.

Find another vendor who can fulfill the delivery dates.

Answers
A.

Find another vendor who can fulfill the delivery dates.

B.

Replan the remaining iterations according to the new installation dates.

Answers
B.

Replan the remaining iterations according to the new installation dates.

C.

Update the product backlog in order to address the delays.

Answers
C.

Update the product backlog in order to address the delays.

D.

Review the procurement agreements to address the situation.

Answers
D.

Review the procurement agreements to address the situation.

Suggested answer: D