A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.

What should the project manager do?

A.

Consult the development team and engage a vendor that is recommended by them.

Answers
A.

Consult the development team and engage a vendor that is recommended by them.

B.

Use a formal approach using procurement policies, procedures, forms, and work instructions.

Answers
B.

Use a formal approach using procurement policies, procedures, forms, and work instructions.

C.

Consult the product owner and engage a vendor that is recommended by them.

Answers
C.

Consult the product owner and engage a vendor that is recommended by them.

D.

Use an agile approach and engage a vendor that delivered well in a previous organization.

Answers
D.

Use an agile approach and engage a vendor that delivered well in a previous organization.

Suggested answer: B