A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.
What should the project manager do?
Consult the development team and engage a vendor that is recommended by them.
Use a formal approach using procurement policies, procedures, forms, and work instructions.
Consult the product owner and engage a vendor that is recommended by them.
Use an agile approach and engage a vendor that delivered well in a previous organization.