List of questions
Related questions
Question 1237 - PMP discussion
A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.
What is the appropriate flow for product development?
Complete development with all functionalities in perfect condition prior to demonstrating to stakeholders to ensure a great first impression.
Complete development for the must-have functionalities only prior to demonstration in order to fail fast and get early feedback.
Complete development for each sprint and demonstrate the product increment to internal stakeholders and the government, without engaging other external stakeholders.
Complete development for must-have functionalities only and demonstrate it to a focus group, but wait until all development is complete to demonstrate it to the government.
0 comments
Leave a comment first