A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.

What should the project manager do?

A.

Ask the scrum master to choose an algorithm based on the pros and cons of each option.

Answers
A.

Ask the scrum master to choose an algorithm based on the pros and cons of each option.

B.

Request a meeting with the product owner to help clarify the user story.

Answers
B.

Request a meeting with the product owner to help clarify the user story.

C.

Invite the sales manager to the next sprint meeting to clarify requirements.

Answers
C.

Invite the sales manager to the next sprint meeting to clarify requirements.

D.

Create a new item in the sprint backlog to determine the appropriate algorithm.

Answers
D.

Create a new item in the sprint backlog to determine the appropriate algorithm.

Suggested answer: D