The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to move its go-live date. What should the project manager do next?

A.

Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.

Answers
A.

Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.

B.

Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.

Answers
B.

Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.

C.

Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.

Answers
C.

Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.

D.

Ask the sponsor to start a new project to support the existing project and help it meet the original time line.

Answers
D.

Ask the sponsor to start a new project to support the existing project and help it meet the original time line.

Suggested answer: A