A new privacy law will go into effect at the beginning of the next calendar year. The project manager realizes the project needs to be compliant with the new law.
What should the project manager do next?
A.
Inform the legal department that the project scope will be updated.
B.
Inform the product owner that the project will continue as planned.
C.
Inform the project steering committee of this constraint.
D.
Inform the project team and create a spike for the next iteration.