Question 1251 - PMP discussion

Report
Export

At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.

What should the project manager do to assess the priorities and meet the new objective?

A.

Communicate the results and negotiate the needed resources and time with the stakeholder.

Answers
A.

Communicate the results and negotiate the needed resources and time with the stakeholder.

B.

Submit a change order request with the new project objective to the project management office (PMO).

Answers
B.

Submit a change order request with the new project objective to the project management office (PMO).

C.

Initiate a crashing routine to gain extra time for the added feature.

Answers
C.

Initiate a crashing routine to gain extra time for the added feature.

D.

Ask the project team to work overtime in order to accommodate the new changes.

Answers
D.

Ask the project team to work overtime in order to accommodate the new changes.

Suggested answer: A