A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event. What should the project manager do first?

A.

Use the contingency fund.

Answers
A.

Use the contingency fund.

B.

Update the risk register.

Answers
B.

Update the risk register.

C.

Prepare a change request.

Answers
C.

Prepare a change request.

D.

Follow the risk response plan.

Answers
D.

Follow the risk response plan.

Suggested answer: D