A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress.

What should the project manager do next?

A.

Capture this in the issue log and escalate it to the project sponsor.

Answers
A.

Capture this in the issue log and escalate it to the project sponsor.

B.

Discuss the need to influence this stakeholder with the sponsor.

Answers
B.

Discuss the need to influence this stakeholder with the sponsor.

C.

Meet with the stakeholder to understand what is causing the delays.

Answers
C.

Meet with the stakeholder to understand what is causing the delays.

D.

Facilitate a brainstorming session to find potential workarounds.

Answers
D.

Facilitate a brainstorming session to find potential workarounds.

Suggested answer: C