During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager react to ensure the project remains successful?

A.

Thank the team member for raising this issue, log it, and move on to the next topic.

Answers
A.

Thank the team member for raising this issue, log it, and move on to the next topic.

B.

Punish the team member for providing negative data that will affect the team's morale.

Answers
B.

Punish the team member for providing negative data that will affect the team's morale.

C.

Focus the discussion on recovery and ways to get back on track.

Answers
C.

Focus the discussion on recovery and ways to get back on track.

D.

Act in a way to highlight the criticality of the situation.

Answers
D.

Act in a way to highlight the criticality of the situation.

Suggested answer: C