At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?

A.

Defer all actions until the next workshop to keep the team focused on other higher priorities.

Answers
A.

Defer all actions until the next workshop to keep the team focused on other higher priorities.

B.

Prioritize the actions with the team, assign individuals who will be responsible for completion, and monitor progress.

Answers
B.

Prioritize the actions with the team, assign individuals who will be responsible for completion, and monitor progress.

C.

Review the critical path and update the project schedule with the newly identified tasks.

Answers
C.

Review the critical path and update the project schedule with the newly identified tasks.

D.

Follow up on each item as soon as possible to ensure timely completion and report the status to management.

Answers
D.

Follow up on each item as soon as possible to ensure timely completion and report the status to management.

Suggested answer: B