A project manager is implementing an enterprise-wide software project. The project has a great business impact and is fully supported by senior management. However, the project manager is facing difficulties getting the support of several key departments.

What should the project manager do?

A.

Ask senior management to communicate with these departments.

Answers
A.

Ask senior management to communicate with these departments.

B.

Understand the user concerns and revisit the stakeholder engagement plan.

Answers
B.

Understand the user concerns and revisit the stakeholder engagement plan.

C.

Hire a project management consultant to help resolve the issue.

Answers
C.

Hire a project management consultant to help resolve the issue.

D.

Convince senior management to introduce rewards to resisting departments.

Answers
D.

Convince senior management to introduce rewards to resisting departments.

Suggested answer: B