Question 1263 - PMP discussion
During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project. What should the project manager do?
A.
Update the contingency plan to take this issue into account.
B.
Meet with the stakeholders to update the risk register and risk management plan.
C.
Study the new regulations with the team and evaluate if there is any impact on the project variables.
D.
Review the procurement documentation and modify requirements as needed.