ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1264 - PMP discussion

Report
Export

A globally distributed project team is running behind schedule due to the lack of team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

A.

Set up a meeting to perform a root cause analysis.

Answers
A.

Set up a meeting to perform a root cause analysis.

B.

Permanently colocate the team for better performance.

Answers
B.

Permanently colocate the team for better performance.

C.

Update the issue log and communicate it to the team.

Answers
C.

Update the issue log and communicate it to the team.

D.

Seek the sponsor's approval to extend the project schedule.

Answers
D.

Seek the sponsor's approval to extend the project schedule.

Suggested answer: A
asked 12/11/2024
Fiertelmeister Tibor
33 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first