Question 1265 - PMP discussion
A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels this new methodology will impact the timely delivery of the project.
What should the project manager do?
Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.
Ask to execute the project with a predictive approach since there is a budget and schedule risk.
Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.
Plan for training on agile tools and techniques used in the defined hybrid methodology for consistent application by all team members.