ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1266 - PMP discussion

Report
Export

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution. What should the project manager do next?

A.

Reject the change because it is contrary to what was agreed to during earlier phases of the project.

Answers
A.

Reject the change because it is contrary to what was agreed to during earlier phases of the project.

B.

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps.

Answers
B.

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps.

C.

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor.

Answers
C.

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor.

D.

Accept the change and use contingency funds to implement this change with minimal schedule impacts.

Answers
D.

Accept the change and use contingency funds to implement this change with minimal schedule impacts.

Suggested answer: C
asked 12/11/2024
Madhanraj N
42 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first