A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?

A.

Analyze the stakeholders.

Answers
A.

Analyze the stakeholders.

B.

Monitor all stakeholders.

Answers
B.

Monitor all stakeholders.

C.

Keep all stakeholders informed.

Answers
C.

Keep all stakeholders informed.

D.

Engage the stakeholders.

Answers
D.

Engage the stakeholders.

Suggested answer: A