In a functional organization, a product analyst is assigned to a short-duration application development effort. The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain.
What should the project manager do?
A.
Enroll the analyst in a capacity-building program, and keep this analyst assigned to the task.
B.
Recognize the analyst's concerns and reassign the task to another team member.
C.
Ask the analyst to use skills to develop the tool, then move development to another team member.
D.
Make sure the analyst has regular pairing meetings with the other team member throughout task execution.
Your answer: