Question 1281 - PMP discussion
A new team member is assigned to a team that consistently delivers each iteration. The new team member does not understand many of the processes followed and begins to negatively impact the schedule.
What should the project manager do?
A.
Allocate time within the iterations to mentor the new team member.
B.
Assign easier activities to the new team member.
C.
Place the new team member on a performance improvement program.
D.
Ask another team member to take some of the new team member's work.