During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the required IT system. What should the project manager do?

A.

Fast track this dependency to avoid delaying the project.

Answers
A.

Fast track this dependency to avoid delaying the project.

B.

Perform Integrated Change Control.

Answers
B.

Perform Integrated Change Control.

C.

Ask IT to prioritize the needed system to meet the schedule.

Answers
C.

Ask IT to prioritize the needed system to meet the schedule.

D.

Include the dependency in the project schedule.

Answers
D.

Include the dependency in the project schedule.

Suggested answer: D