The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck.

The team has researched a tool that could resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

A.

Escalate the issue with the product owner.

Answers
A.

Escalate the issue with the product owner.

B.

Reduce the testing scope of the backlog.

Answers
B.

Reduce the testing scope of the backlog.

C.

Add developers to remove the backlog.

Answers
C.

Add developers to remove the backlog.

D.

Enroll team members in training on the tool.

Answers
D.

Enroll team members in training on the tool.

Suggested answer: D