Question 1288 - PMP discussion
A risk was identified at the beginning of a project, and a response plan was established.
Unforeseen consequences resulted in a higher level of risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk mitigation plan.
What should the project manager do?
A.
Submit the new response plan to the stakeholders for their review.
B.
Obtain management approval prior to implementing the new risk response.
C.
Implement the new response to address the risk.
D.
Use the management reserve to mitigate the risk.