Question 1287 - PMP discussion
A leader from project B consistently reaches out to a team member in project A for assistance.
What should project A's project manager do?
A.
Tell project A's team member to ignore project B's leader.
B.
Talk with project B's leader to discuss possible impacts to both projects.
C.
Allow project B's leader to continue building relationships.
D.
Ensure project A's team member can finish the work committed to project A.