A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of contract to sign with the vendor responsible for migrating the systems. The project manager is concerned about controlling finances while delivering results.

How should the project manager address this situation?

A.

Sign a single agreement for the whole project.

Answers
A.

Sign a single agreement for the whole project.

B.

Confirm payment after each project retrospective.

Answers
B.

Confirm payment after each project retrospective.

C.

Negotiate payment after all project migration is completed.

Answers
C.

Negotiate payment after all project migration is completed.

D.

Use fixed-price increments as user stories are completed.

Answers
D.

Use fixed-price increments as user stories are completed.

Suggested answer: D