A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included.
What should the project manager do next?
A.
Review the terms and conditions of the contract.
B.
Submit a change request to include the manual.
C.
Review the stakeholder engagement plan.
D.
Add the needed manual and update the risk log.