A project manager is leading a project at a contracting company, and the project team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

A.

Follow the proper change control process and evaluate the change for further impact.

Answers
A.

Follow the proper change control process and evaluate the change for further impact.

B.

Perform frequent reviews with the customer to ensure that the product is working as expected.

Answers
B.

Perform frequent reviews with the customer to ensure that the product is working as expected.

C.

Manage the scope baseline to influence the factors that drive change.

Answers
C.

Manage the scope baseline to influence the factors that drive change.

D.

Work with the customer to ensure the feature adds value.

Answers
D.

Work with the customer to ensure the feature adds value.

Suggested answer: A