Question 1306 - PMP discussion
The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.
What should the project leader do?
A.
Escalate the impediment and associated risks to the business sponsor.
B.
Identify the impediment and associated risks at the daily standup.
C.
Report the impediment to the functional manager.
D.
Identify the impediment during the retrospective.