List of questions
Related questions
Question 1307 - PMP discussion
A project manager is working on a project using a hybrid approach. The project is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company, which was approved by their functional manager.
What should the project manager do first in this situation?
A.
Ask the functional manager for an immediate replacement for the team member.
B.
Review the risk management plan and mitigation plan to understand the impact of this issue.
C.
Ask the functional manager why a decision was made without consulting them.
D.
Use soft skills to influence the team member to stay until the project is completed.
Your answer:
0 comments
Sorted by
Leave a comment first