During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much experience in development.

What should the project manager do?

A.

Allow the team to reevaluate the tasks and determine how they should be allocated.

Answers
A.

Allow the team to reevaluate the tasks and determine how they should be allocated.

B.

Request that all quality assurance tasks be allocated to the new resource.

Answers
B.

Request that all quality assurance tasks be allocated to the new resource.

C.

Move the developer to another team and look for a replacement developer.

Answers
C.

Move the developer to another team and look for a replacement developer.

D.

Maintain the same task allocation structure to avoid any disruption in the project team.

Answers
D.

Maintain the same task allocation structure to avoid any disruption in the project team.

Suggested answer: A