A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three.)

A.

Send out a survey to review the preferred method, timing, and frequency for communications.

Answers
A.

Send out a survey to review the preferred method, timing, and frequency for communications.

B.

Review the communications strategy with the team regularly with a view for continuous improvement.

Answers
B.

Review the communications strategy with the team regularly with a view for continuous improvement.

C.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

Answers
C.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

D.

Require the team to have daily mandatory meetings with the project management office (PMO).

Answers
D.

Require the team to have daily mandatory meetings with the project management office (PMO).

E.

Recommend the use of formal written documentation in all project communications.

Answers
E.

Recommend the use of formal written documentation in all project communications.

Suggested answer: A, B, C