In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.

What should the project manager do to avoid a reoccurrence of this scenario?

A.

Ensure the content of the project report is clearly understood and request any necessary feedback.

Answers
A.

Ensure the content of the project report is clearly understood and request any necessary feedback.

B.

Ensure that all product features are completed as per the communicated specifications before releasing to market.

Answers
B.

Ensure that all product features are completed as per the communicated specifications before releasing to market.

C.

Send a detailed report to each steering committee member ahead of the meeting.

Answers
C.

Send a detailed report to each steering committee member ahead of the meeting.

D.

Invite critical stakeholders to the daily project review meetings to ensure their full engagement and involvement.

Answers
D.

Invite critical stakeholders to the daily project review meetings to ensure their full engagement and involvement.

Suggested answer: A