A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.

What should the project manager do?

A.

Add collaboration tools to the communications management plan.

Answers
A.

Add collaboration tools to the communications management plan.

B.

Allow collaboration to smooth out communication between team members.

Answers
B.

Allow collaboration to smooth out communication between team members.

C.

Escalate these communication challenges to the project sponsor.

Answers
C.

Escalate these communication challenges to the project sponsor.

D.

Organize a team meeting to resolve the communication challenges.

Answers
D.

Organize a team meeting to resolve the communication challenges.