Question 1314 - PMP discussion
A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.
Which technique will best serve this purpose?
A.
Power user grid
B.
Personas
C.
Power influence grid
D.
Salience model