In a fixed time and budget project, the customer wants the development of a core component to be based on agile practices, as the final scope of the requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two.)

A.

Establish a governance committee to review the contract delivery.

Answers
A.

Establish a governance committee to review the contract delivery.

B.

Provide alternatives to scope change at specific project phases within the contract.

Answers
B.

Provide alternatives to scope change at specific project phases within the contract.

C.

Tier the contract for fixed and agile components.

Answers
C.

Tier the contract for fixed and agile components.

D.

Limit the number of iterations for development in the contract.

Answers
D.

Limit the number of iterations for development in the contract.

E.

Require that only internal resources be utilized for this project.

Answers
E.

Require that only internal resources be utilized for this project.

Suggested answer: C, D

Explanation:

Tiering the contract for fixed and agile components (Option C) and limiting the number of iterations for development (Option D) are the most effective controls for managing development costs and ensuring the profitability of the project while allowing for the flexibility needed in agile practices.