Question 1324 - PMP discussion
A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.
What should the project manager do?
A.
Forward the project status reports.
B.
Escalate this to the project sponsor.
C.
Request a meeting with the stakeholder.
D.
Design an updated status report.
Your answer: