A new project manager has been assigned to an environmental project. After reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

A.

It is imperative that established performance metrics are met.

Answers
A.

It is imperative that established performance metrics are met.

B.

Injury or loss incidents could delay project deliverables.

Answers
B.

Injury or loss incidents could delay project deliverables.

C.

The project manager must follow their employer's organizational process assets (OPAs).

Answers
C.

The project manager must follow their employer's organizational process assets (OPAs).

D.

The project manager is obligated to comply with the project location's regulatory requirements.

Answers
D.

The project manager is obligated to comply with the project location's regulatory requirements.

Suggested answer: D