A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain. When attempting to gain an understanding of the risks for this agile project, what is the primary tool the project manager should employ?

A.

Workshops for risk avoidance

Answers
A.

Workshops for risk avoidance

B.

Probability assessments

Answers
B.

Probability assessments

C.

Collaborative discussions

Answers
C.

Collaborative discussions

D.

Interview with the project champion

Answers
D.

Interview with the project champion

Suggested answer: C