In the middle of an iteration, the product owner tells the agile team that the government has updated legal requirements. This will result in some changes in the product definition.

How should the project manager handle this situation?

A.

Continue work and ask the product owner to assess the changes and add/remove the stories as needed in the backlog.

Answers
A.

Continue work and ask the product owner to assess the changes and add/remove the stories as needed in the backlog.

B.

Ask the product owner to add new changes to the bottom of the backlog in order to handle the modifications as a change request.

Answers
B.

Ask the product owner to add new changes to the bottom of the backlog in order to handle the modifications as a change request.

C.

Review the iteration backlog because the product definition has changed and needs to be reassessed before continuing the project.

Answers
C.

Review the iteration backlog because the product definition has changed and needs to be reassessed before continuing the project.

D.

Ask a business analyst to assess the changes and then add/remove the stories in the backlog and prioritize them by business value.

Answers
D.

Ask a business analyst to assess the changes and then add/remove the stories in the backlog and prioritize them by business value.

Suggested answer: C