A project manager has just taken over a project that is in the requirements gathering phase. A stakeholder indicates that they have not received any progress updates even though reports have been sent on a weekly basis.
What should the project manager do to ensure all stakeholders are receiving proper information about the project?
A.
Hold a steering committee meeting with all stakeholders to provide a comprehensive update on the project progress.
B.
Create daily progress reports and send them to all stakeholders.
C.
Assess all of the project stakeholders and document their preferred communication method and frequency.
D.
Include stakeholders in the weekly status meetings with the team.