Question 1345 - PMP discussion
A project manager is assigned to deliver a development project with subcontracted resources from a sister company. What should the project manager do to ensure a smooth inclusion of the new subcontracted resources?
A.
Share the project team ground rules with the subcontractors.
B.
Schedule a formal meeting to cover the mission and vision.
C.
Organize a team-bonding exercise with the subcontractors.
D.
Facilitate a working session to review the ground rules.
Your answer: