According to the project contract, the delivery date is approaching. However, one important material is still not on site. The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

A.

Engage the project team to look for alternatives to find a solution.

Answers
A.

Engage the project team to look for alternatives to find a solution.

B.

Record it in the risk register.

Answers
B.

Record it in the risk register.

C.

Ask the client to help solve the problem.

Answers
C.

Ask the client to help solve the problem.

D.

Start procuring this material from another supplier.

Answers
D.

Start procuring this material from another supplier.

Suggested answer: A