Question 1355 - PMP discussion
A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed for the product.
What should the project manager do to continue with the delivery plan and return to the expected velocity?
Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.
Replace poorly performing team members with more experienced members, setting an example of accountability for the team.
Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.
Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.