ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1361 - PMP discussion

Report
Export

At the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

A.

Develop requirements and designs to support a faster product release.

Answers
A.

Develop requirements and designs to support a faster product release.

B.

Outsource development of the product to a third party with more experience.

Answers
B.

Outsource development of the product to a third party with more experience.

C.

Recommend an agile approach so the project can be delivered iteratively.

Answers
C.

Recommend an agile approach so the project can be delivered iteratively.

D.

Emphasize the adoption of a predictive approach to minimize ambiguity.

Answers
D.

Emphasize the adoption of a predictive approach to minimize ambiguity.

Suggested answer: C
asked 12/11/2024
Mustafa Kubha
44 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first