A functional manager is concerned that the project's quality management techniques have advanced beyond the department's capabilities and wants the project team to review all quality management activities in two full-day workshops the following week. What should the project manager do next?

A.

Indicate that this was a not a requirement identified during project planning and it is outside of the scope.

Answers
A.

Indicate that this was a not a requirement identified during project planning and it is outside of the scope.

B.

Draft a project decision request to include in the scope for the current iteration and ask the sponsor to approve.

Answers
B.

Draft a project decision request to include in the scope for the current iteration and ask the sponsor to approve.

C.

Explain that the team is fully dedicated to the current sprint activities and negotiate a mutually agreeable time.

Answers
C.

Explain that the team is fully dedicated to the current sprint activities and negotiate a mutually agreeable time.

D.

Add this to the project backlog and have the product owner determine where it fits in terms of priority.

Answers
D.

Add this to the project backlog and have the product owner determine where it fits in terms of priority.

Suggested answer: C