A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.
Which action should the project manager take next?
A.
Ask the team to wait until they are able to update the requirements specifications.
B.
Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.
C.
Meet with the development team to review and assess the requirements specifications.
D.
Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.