A customer discovered quality issues with the latest deliverables. However, the project team immediately resolved the issues.

Now that the project is back on track, what should the project manager do next?

A.

Perform lessons learned to ensure the issue does not happen again.

Answers
A.

Perform lessons learned to ensure the issue does not happen again.

B.

Reassess the risk log to ensure it is up to date.

Answers
B.

Reassess the risk log to ensure it is up to date.

C.

Schedule a team meeting to review the issue.

Answers
C.

Schedule a team meeting to review the issue.

D.

Monitor quality metrics to ensure the project continues as planned.

Answers
D.

Monitor quality metrics to ensure the project continues as planned.

Suggested answer: A