Question 1365 - PMP discussion

Report
Export

A project manager uses a laissez-faire leadership style with a newly hired project team. The project manager quickly notices that team members are underperforming, the schedule is delayed, and the project is overbudget.

What should the project manager have done at the start of the project?

A.

Managed the team as necessary and allowed them to work on their own

Answers
A.

Managed the team as necessary and allowed them to work on their own

B.

Adapted a direct management style according to the project team's needs

Answers
B.

Adapted a direct management style according to the project team's needs

C.

Established goals and provided the project team with sufficient authority to work

Answers
C.

Established goals and provided the project team with sufficient authority to work

D.

Adapted a servant leader management style to support the team's development

Answers
D.

Adapted a servant leader management style to support the team's development

Suggested answer: C