Question 1371 - PMP discussion
A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important milestone in a week.
What should the project manager do next?
Perform market research to find out if there are other vendors that can produce similar kinds of materials.
Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.
Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.
Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.