List of questions
Related questions
Question 1372 - PMP discussion
Multiple agile teams are working on a product deliverable. During the last few iterations, one of the teams received several unplanned, nonproduction support requests from other teams. This affected the velocity of the team and the planned deliverable.
What should the project manager do in this situation?
A.
Tell the team to extend and complete the planned deliverable as well as incoming requests.
B.
Ask the team to accommodate most of the requests in each of the iterations.
C.
Inform members of the other teams to add these requests directly in the iteration backlog.
D.
Direct the team to only focus on the planned deliverable and not take on any unplanned activity.
Your answer:
0 comments
Sorted by
Leave a comment first