Question 1390 - PMP discussion

Report
Export

A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing. Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.

What should the project manager have done to avoid this situation?

A.

Set up weekly status meetings to review team progress, prepared weekly status reports to track progress, and regularly escalated delays.

Answers
A.

Set up weekly status meetings to review team progress, prepared weekly status reports to track progress, and regularly escalated delays.

B.

Established daily standup meetings to track and report on team progress and escalated delays to stakeholders as they occurred.

Answers
B.

Established daily standup meetings to track and report on team progress and escalated delays to stakeholders as they occurred.

C.

Met with the team, allowed team members to make decisions about what to do, and established performance goals.

Answers
C.

Met with the team, allowed team members to make decisions about what to do, and established performance goals.

D.

Conducted routine meetings and identified team members who are under performing.

Answers
D.

Conducted routine meetings and identified team members who are under performing.

Suggested answer: C